Hub Foundation has over five decades of experience working on large scale projects throughout the Northeast.

Projects

Slurry Walls and
Load Bearing Elements

Bullfinch Crossing Residential Tower

Boston, MA

We completed our first slurry wall project at a particularly challenging and restricted site in downtown Boston at the intersection of Congress Street and New Sudbury Street. At 90 by 160 feet, it's extremely small for the extensive foundations we installed and the sheer number of big rigs involved; it was like a game of Tetris.

The contract called for a foundation supporting a 42-story tower consisting of an earth retaining system of drilled-in-place soldier beams along New Sudbury Street and a mini pile earth retaining system adjacent to 115-kilovolt buried power lines. The design specified 100 mini piles due to access constraints; they were placed as close as 18 inches to the power lines. The core of the building is supported by heavily reinforced slurry wall; the columns supported the LBEs, one of which had a 17-by-730-pound column with two-inch cheek plates.

Our Liebherr 895 220-ton capacity crane handled rebar cages and site support. We placed three caissons where existing utilities prevented access with the rectangular LBEs. We installed the slurry walls and LBEs with a Leffer Clamshell and the Bauer Cutter BC35. The Bauer MAT Plant, or desander, cleaned the slurry. Our Derrick Centrifuge facilitated the final processing of the slurry. We installed six additional drilled shafts to support a tower crane foundation. In addition to our drilling rigs, we maneuvered four cranes, a concrete pump truck, and an excavator to carry out the project.

Drilling in tight confines

Moxy Hotel

Boston, MA

Hub specializes in providing deep foundation solutions in very tight site confines that require thorough logistical coordination between us, the owners, and the GC. On this project, we were constantly monitoring the neighboring properties while managing the tooling and casing to drill 3, 3.5, 4 and 5 foot diameter shafts in the theater district of downtown Boston for The Moxy Hotel, part of the Marriott group.

Downtown Boston

Bullfinch Place

One Congress Street, Boston, MA

Hub is capable of providing many deep foundation techniques; on Bullfinch Place we are installing SOE, LBEs, slurry walls, drilled shafts, and drilled mini piles, all on one constrained urban site for a new building in downtown Boston.

Complex bridge work

Woods Memorial Bridge

Medford, MA

Hub was contracted to install drilled shafts up to 165 feet long, integrated pile driving and secant pile wall foundation, SOE, and high capacity drilled mini piles for the replacement of two bridges in Medford, Massachusetts. This project required us to work in close proximity to vehicular and pedestrian traffic, public transportation, and bridge demolition. Hub successfully negotiated these restrictions on a three-phase job for MassDOT, which owns the bridges themselves and owns the general contractor on the job, the MBTA. Some of the more interesting challenges Hub performed on this project were six bidirectional axial load tests, environmentally friendly construction techniques to protect the water, and remote spoil handling and water disposal.

Bridge Support

Memorial Bridge

Portsmouth, NH - Kittery, ME

The Memorial Bridge for US Rt. 1 over the Pistataqua River included 11 drilled shafts for the Kittery approach, 8 drilled shafts for the Scott Ave. approach, and 74 micropiles drilled through the existing piers to support the new structure. The project was completed between April and December of 2012.

Deep Foundations

The Broad Institute

Cambridge, MA

The Broad Institute required the installation of 27 drilled shafts and 13 micropiles in a lot adjacent to an existing parking structure, with an additional 55 micropiles drilled with limited access and low headroom in the basement of the existing parking structure to support supercolumns. A 650-ton pile load test was performed on a 9⅝ inch micropile to verify the innovative pile design utilized in the project. Combined, the foundation elements support a new 18 story structure both adjacent to and above the parking structure. Hub completed the project in July 2012 and it was featured in the September / October 2013 issue of DFI's Deep Foundations magazine.

Challenging Terrain

Logan Airport

Boston, MA

MassPort required the replacement of a light pier 800' out into the Boston Harbor. Hub was contracted to install 7' diameter drilled shafts for eight piers, off of a barge, with difficult soil conditions and very hard rock. Hub was able to accomplish this project by using our in-house expertise and drilled mini pile division to design, drill, and place a template with pipes seated into the rock, so that we could finish installing the shafts in accordance with the plane and specifications.

Hub Foundation Co., Inc.

139 Billerica Rd.

Chelmsford, MA 01824